Digital Access

Digital Access
Access morrisherald-news.com from all your digital devices and receive breaking news and updates from around the area.

Mail Delivery

Mail Delivery
We’ve got you covered! Get the best in local news, sports, community events, with focus on what’s coming up for the weekend. Weekly packages.

Text Alerts

Text Alerts
Choose your news! Select the text alerts you want to receive: breaking news, weather, and more.

Email Newsletters

Email Newsletters
Have our latest news, sports and obituaries emailed directly to you Monday through Friday so you can keep up with what's happening in Morris and Grundy County.

Generating Station Unit 1 completes refueling outage

Unit 1 returned to full power Thursday

BRACEVILLE – Operators returned Braidwood Generating Station Unit 1 to full power Thursday morning following the completion of the unit’s 17th refueling outage on Monday.

During the 21-day outage, Exelon employees and supplemental workers performed more than 13,000 activities, including equipment upgrades, safety inspections, tests and plant improvements. The unit began its scheduled refueling outage Sept. 9.

“We appreciate the efforts of our employees and the more than 1,150 supplemental workers that supported us,” said Braidwood Site Vice President Mark Kanavos.  “The work performed during the outage will help ensure safe, reliable and efficient operation of Unit 1.”

Braidwood Unit 2 continued to operate during the Unit 1 refueling outage.

Braidwood Generating Station is approximately 60 miles southwest of Chicago. The station’s two nuclear energy units can produce a total of more than 2,300 megawatts at full power – enough electricity to power more than 2 million typical homes.